On our Wood Wharf J1/J3 project, this week we installed the unit no. 1,980 out of a total 2,277 on the lower J1 tower with its 34 floors. This was the last one before the hoist infill units, which will be installed only after the hoist dismantle.
Great result of the whole team: with the installation speed of 3.5 days per floor, we are miles ahead of Programme and we have achieved the agreed goal of closing the J1 tower facade by Christmas!
We still have 15 floors to go on the higher J3 tower.
Great job Sipral and CTR Site Services Ltd.